EBZ260 Roadheader for highway tunnel
- Roadheader used : EBZ260
- Project start date : 2014/3/20
- Project completion date : 2015/4/22
- Surrounding rock grade: F5
- Rock hardness at the beginning of the tunnel : 50MPa;
- Rock properties: sand stone mixed with volcanic pebbles.
- Tunnel section 11m width × 10m height, the first layer (11 * 7 widthxheight);
- Working nine hours a day, progress achieved was 154cbm / day;